Addendum #1
8/17/2016
Question 1. Please advise the type of Spray Lining that is specified for this contract.
Response: Please reference specification sections 02957, 02958 and 02959.
8/31/2016
PLEASE NOTE THE BID OPENING DATE HAS BEEN CHANGED FROM SEPTEMBER 12, 2016 TO SEPTEMBER 16, 2016 AT 2:00 P.M. LOCAL TIME.
9/2/2016
Question 2. Does the backfill at Section 2 need to be CLSM? If not please provide the details on backfill.
Response: Yes.
Question 3. During the shutdowns, can the work be completed 24 hours per day?
Response: Yes, see Specification 01000 Paragraph 1.3 A. 2.
Question 4. With cutting in the pipe, cleaning, performing the pipe work, installing the new pipe sections… we believe the 6 outages is not enough to perform the work. Can the outages be increased? Is 12 outages acceptable?
Response: No.
Question 5. Does the backfill for the exploratory excavation need to be tested? If so can you provide the testing requirements?
Response: Yes, see Specification Section 02250 for testing and compaction requirements.
Question 6. Under the unit prices, what is the difference between Item C and Item D?
Response: Item C includes CA-7 course aggregate stone, Item D includes CA-6 course aggregate stone.
Question 7. What are the pavement requirements?
Response: See Specification 02500 Paragraph 3.2 C.
Question 8. Do the joints of the pipe need to be “filled In” to before the liner is installed.
Response: No, but per specifications the liner shall provide continuous coverage over its entire length.
Question 9. What is the owner’s estimate on this project?
Response: The engineers estimate is $1.38 million.
Additional Documentation:
Addendum Revised Spec Page
Pre-Bid Meeting Q & A
Revised Bid Form
Pre-Bid Meeting Sign In Sheet