BId #21043 - Route 83 Force Main Realignment

Addendum #1


March 16, 2021

Question:  Is there an estimated project value available for the above project?

Response:  The estimated project value is $300,000.

Question:  Is there a date of completion set yet?

Response:  The substantial completion is 90 days.

April 2, 2021

Question:  Do you have the pre-bid meeting attendance sheet for the above project?

Response:  The following vendors attended the pre-bid meeting:

Joel Avitia - Berger Excavating Contractors, Inc.

Doug Abbey - Bolder Contractors, Inc.

Nicholas Neri - John Neri Construction Co

 