Bid #23053 - 2023 Wildwood Water Main Replacement
Addendum #1
May 18, 2023
Addendum #1
Question: Was the pre-bid meeting mandatory?
Response: No.
May 8, 2023
Question: What type of pipe to be installed on the said project?
Response: The primary pipe to be installed in this project is 8 inch PVC pressure rated pipe conforming to ASTM D1784 and AWWA C900 with a minimum wall thickness corresponding to DR 18.