Lake County Addendum Forum

Bid #24264 - Rollins Road Bubbler Replacement

Addendum #1

March 8, 2024

Question:  Do you have an estimated start date (or month) for this project?

Response:  The Bid Opening is Friday April 19, 2024.  It is expected that this will be before the County Board on the June 11, 2024 meeting.  The award and notice to proceed would be appropriate to the final County Board action.

April 17, 2024

Question:  Is there an estimated cost value associated with this project?

Response:  The EOPCC (Engineer’s Opinion of Probable Cost of Construction) is $90,000.