Bid #25196 - Wildwood Water System Controls Improvements & SCADA Modernization

Addendums

Addendum #1

Question:
I am inquiring to ask if there is a construction cost estimate or budget associated with the Wildwood Water System Controls Improvements and SCADA Modernization Project.

Response:
Engineer’s latest estimate of the construction cost is $ 785,000.