Bid item #12 is a lump sum bid item for “Cleaning and prepping exposed steel reinforcement and steel wire.” Page 9 of 35 in the specification acknowledges there are “a few sections of pipe and portions of the blind 90 degree bend that may have exposed steel reinforcement and/or steel wire.” The spec says “after the sewer cleaning the contractor shall review the condition of all exposed steel.” If cleaning reveals additional locations of steel that require prepping, will there be additional compensation for this work that’s not currently identified?

Response:  Based on our review of the sewer videos LCPW anticipates the following areas will have to  prepped because of exposed steel:
1) The bling 90 degree bend
2) 50 LF of pipe immediately adjacent and upstream of the blind 90 degree bend on Wilson
3) 50 LF of pipe immediately adjacent and downstream of the blind 90 degree bend on Rollins
4) One section of pipe on Rollins a distance west of the blind 90 degree bend.

If cleaning revels additional locations there would be additional compensation.

January 26, 2021

Q#1: We’ve built a lot of constructions projects and haven’t had portable facilities on-site during our project. Can you change this from a requirement to a recommendation?

Page 2 of 35 States:
Equipment: Portable facilities must at a minimum include portable washroom facilities and hand washing stations. All other facilities must be discussed at the pre-construction meeting for approval by the County.

Construction Requirements: The portable restroom and hand washing stations shall be serviced on a weekly basis or as determined necessary by the County. The location of such facilities shall be approved by the County prior to their delivery.

A#1: NO, bid as stated in the specifications

Q#2: At the 13 minute mark of the video entitled “MH 72BB01 to MH 72AA29 (blind 90 degree bend) 2021-01-04”, the pipe makes a 90 degree turn to the left. There is an elevated bench with flow coming in from the right side. Does the scope of this project include any rehabilitation of that elevated bench or associated chamber or is this project strictly rehabilitating the pipeline? Can you clarify the exact scope of this project when talking about the “blind 90 degree bend?”

A#2: The Blind 90 Bend Lining is Bid Item #9.  Scope of work includes lining of the entire 90 degree bend the underside of the top slab, sides and bench areas.  The Junction Chamber that can be seen through the opening to the right is work that is part of another Bid.  (See attached Revised Exhibit 1).

Q#3: The spec book shows a cleaning spec on pages 15-16, and a separate pages 23-24. Which one is appropriate for Line Item No.2?

A#3: Cleaning of the two sections of 42” sewer and the blind 90 degree bend is considered incidental and required prior to ling of the pipes and the blind 90 degree bend prior to application of the chosen product(s).

Q#4: Is there any cleaning work in the 4’-10” x 8’-3” x 28’x9” Junction Chamber Structure?

A#4: NO, The Junction Chamber Structure work is part of another Bid. (See attached Revised Exhibit 1).  ADDITIONAL EXHIBIT FOR THIS BID CAN BE FOUND UNDER THE DOCUMENTS SECTION IN THE ORIGINAL BID POSTING.

Q#5: Will Quadex GeoKrete to be considered as an approved equal geopolymer liner (GeoSpray Product) for the rehabilitation of the 42-inch transmission sewers and the blind 90 degree bend?

A#5: NO, not at this time but this product may be submitted for review by the low bidder that is selected. 

January 25, 2021

Question:  Will LCPW be able to give me some info regarding water (hydrant) usage for this project. Did Lake County Public Works Department make arrangements?

Response:  LCPW has made no arrangements with any nearby community for use of their hydrants.

LCPW would supply water to fill a water tanker truck at our Lincoln Well House site located in Fox Lake Hills at the NE corner of W Lincoln Drive and N Fairview Lane.

January 22, 2021 - Addendum #4

ADDITIONAL DOCUMENTATION FOR THIS BID CAN BE FOUND UNDER THE DOCUMENTS SECTION IN THE ORIGINAL BID POSTING.

GENERAL:
1) This project can be bid independently of Bid#21004 (Junction Chamber Rehabilitation) or in conjunction with that bid.  Bidders are not required to bid both projects.
2) In the Agreement, page A-2, Paragraph 4.02 A the days noted to substantial and final completion are calendar days.
3) In the Invitation to Bid, Page IB-9, Paragraph 17.06 change “will not” to read “may”.
4) Bidders are responsible for providing a letter of credit to LCDOT for the work within Lake County DOT right of way.   The amount of the Letter of Credit will be approximately $35,000.

PLANS:
1) None

SPECIFICATIONS:
1) The first paragraph on sheet 12 of the sewer lining specifications references the 2013 videos shall be updated to include reference to the 2021 videos as well and is modified as listed below.
Bidders must review the CCTV inspection records, prior to preparing and submission of their Bid. The CCTV inspection records provided are from 2013 and 2021. The various issues identified in the videos shall be remediated by the sewer lining contractor.  If no specific line item is included in the contract it shall be assumed it is included in the pay item for the applicable liner system.

2) The pay item “Televising/Still Color Photos of Blind 90 Degree Bend” shall be modified to read “Televising/Still Color Photos of Blind 90 Degree Bend After Product Application” in both the specifications and on the bid form.

3) Under section 1.4 of the “Spray in Place Epoxy Liner” specification item 3 under Product Data on sheet 19 shall be removed and replaced with the following:
The liner shall be designed for a 50 year service life for durability and be designed to ensure the liner does not delaminate from the host pipe over its service life.

4) Under section 1.4 of the “Spray in Place Polyurea Liner” specification item 3 under Product Data on sheet 26 shall be removed and replaced with the following:
The liner shall be designed for a 50 year service life for durability and be designed to ensure the liner does not delaminate from the host pipe over its service life.

5) On page 35 of the specifications item #3 under Cementous liner shall be removed from the “Sewer and Blind 90 Bend Structural Rehabilitation Prior to Topcoat Lining System” shall be removed from this pay item and respectively added to the “42” Transmission Sewer Lining – Epoxy” and “42” Transmission Sewer Lining – Polyurea” pay items.

6) The first paragraph following the Detailed Design and Shop Drawing Submittal on sheet 12 shall be modified as listed below.

Submit detailed design of geopolymer spray lining after field verification of pipe dimensions, pipe depth, water table (assumed 5’ below surface), and other design parameter confirmation and shall be in accordance with the requirements listed below in the Liner Design portion of this specification. The design and calculations must be prepared and stamped by a Professional Engineer licensed in the State of Illinois and shall comply with the requirements listed herein. The professional engineer shall be authorized to perform such work.

EXHIBITS:
1) North Service Area 8” Bypass Exhibit - Per discussions with LCDOT the existing 24” storm culvert under Wilson Road can be utilized as a conduit for the sewer bypass piping.
2) LCDOT Performance Guarantee Forms are attached for Bidders information.
3) The Blackhawk flow analysis report prepared by Baxter&Woodman listed in the bid documents was not included in the original bid package. This document is included in this addendum.

BID FORM and NOTES:
1) Pay items 14 and 17 shall have the unit modified to be lump sum and the quantity updated to 1 to follow the language included in the specifications.
2) Paragraph C titled inspection on page 30 shall be removed in its entirety and replaced with “Covered in other specifications.”
3) The following pay item shall be added as Alternate Pricing Item D to the Epoxy Liner specification. “Blind 90 Bend Lining – Epoxy”.
4) The following pay item shall be added as Alternate Pricing Item E to the Polyurea Liner specification. “Blind 90 Bend Lining – Polyurea”
5) Bid Note 1 on page B-4 shall be deleted and replaced with the following “To be considered responsive, bidder must supply pricing information for bid items 1 to 18 with the exception of bid item 9 and bid item 10:
• If pricing is not provided for item 9 pricing MUST be provided for bid alternate items A and D or alternate items A and E.
• If pricing is not provided for item 10, pricing MUST be provided for alternate items A and B or alternate items A and C.
NOTE:
1) The base bid amount for items 1 to 18 or the base bid amount less items 9 and 10 with the chosen alternate items for 9 and 10 as noted above will be utilized to determine the lowest base bid amount.
2) If not providing a price for items 9 or 10 or a particular corresponding alternate place a “0” zero for that items total price.

6) A revised bid form is included with this addendum.

January 6, 2021 - Addendum #3

Attached is a web-link provided by Gewalt Hamilton Associates, Inc. (GHA) so that you can download the following  five 42” sewer videos:

https://drive.google.com/file/d/1BLq93Y3HiMg23h3Xp4Tjme_qaNNjAdYF/view?usp=sharing

Rollins Road:
MH 72AA28 to MH 72AA29 (blind 90 degree bend)   2013-09-04

MH 72AA28 to MH 72AA29 (blind 90 degree bend)   2013-09-10

MH 72AA28 to MH 72AA29 (blind 90 degree bend)   2021-01-04

Wilson Road:
MH 72BB01 to MH 72AA29 (blind 90 degree bend)   2013-09-04

MH 72BB01 to MH 72AA29 (blind 90 degree bend)   2021-01-04

December 29, 2020- Addendum #2

Q#1: What is the estimated price value for the project in the subject line? When is the anticipated construction start date for this project?
A#1:
Our engineer’s estimate of cost is $342,000

Approximate key dates after the bid opening on 2/1/21 are:
3/9/21 – County Board Meeting
4/01/21 – Purchase order / Notice to Proceed sent
May 2021 – Start of construction

December 28, 2020- Addendum #1

Q) Do you anticipate extending the bid due date? A) No, not at this time.
Q) What additional details are you willing to provide, if any, beyond what is stated in bid documents concerning how you will identify the winning bid? A) No additional details beyond what is already stated in the Bid are available at this time.
Q) Was this bid posted to the nationwide free bid notification website at www.mygovwatch.com/free? A) No
Q) Other than your own website, where was this bid posted? A) The procurement opportunity was posted and advertised in accordance with the Lake County Purchasing Ordinance guidelines. Lake County has no knowledge of the solicitation being posted beyond the Lake County website.