May 11, 2020
Bidders are directed to review revised Spec Sections 07 18 00 and Sections 07 95 00 issued by CTL Group and dated 5/8/20. The reissued spec sections include approved alternate products.
May 7, 2020
Addendum
Revised Electrical Drawing
Revised Structural Drawing
April 29, 2020
Question: Do Bird-X All Steel Spikes qualify as an approved equal and can they be used on this project?
Response: Bird X All Steel Bird Deterrents as manufactured by Bird-X Inc of Chicago, IL are hereby added as an additional approved manufacturer for this project. Contractor shall take care to properly prepare subsurface and utilize manufacturer’s recommended adhesive attachment.
April 24, 2020
Question: Is there a pre-bid meeting sign-in sheet available?
Response: Please see the attached list of participants.
Clarification:
Lake County will be accepting only electronic bid submissions for Invitation for Bid #20069 – Lake County Parking Garage Repair & Rehabilitation.
Please follow the steps below to upload your electronic Bid Submission:
- Go to www.lakecountypurchasingportal.com
- Click on the Bid Number: 20069
- Click on register for this bid
- Enter your username and password
- Under the Submittals section you will be able to upload your bid submittal
- Click on the browse button
- Navigate your computer and select the appropriate file
- Multiple files can be uploaded, each file can be no more than 20 MB
- Click on save submittals
- Close the browser
*Please note: Responses are due at 11:00 a.m. local time on Tuesday, May 12, 2020. Please allow sufficient time for any technical issues you may have and upload your bid early. Please email Purchasing at purchasing@lakecountyil.gov to receive confirmation that we have successfully received your submissions.
Please follow the following steps to attend the Public Bid Opening:
- Go to www.lakecountypurchasingportal.com
- Click on the “Under Review” tab
- Click on the Bid Number: 20069
- Click on the “Events” tab
- Join the Zoom Meeting by clicking on the meeting link
- Please plan on joining the meeting at least 5 minutes early and mute your microphone
April 20, 2020
Question: Does the prospective bidder have to be a unionized contractor to bid on the project?
Response: The prospective bidder must comply with the Illinois Prevailing Wage Act and meet the requirements in the responsible bidder affidavit.
Question: What is the estimated price value for this project?
Response: $1,200,000
Question: When is the anticipated start date for construction?
Response: July 2020.