Question |
Response |
Signage Scope Confirmation: Please confirm the signage scope of work is only in the additional administrative building, and there is no additional signage work in the existing building. |
Signage will be required only as part of new work. |
Will Architect waive the AISC certification standard for the steel fabricator. |
AISC certification is not waived for shop fabrication. However, field welds where indicated on the plans needs only be performed by AWS certified welders. The reason for keeping the certification for shop fabrication is that this structure is a moment resisting frame without wall bracing. |
Please confirm if there are any existing CAD drawings for the building and the land for grading. |
Yes, there are CAD/REVIT files available |
Please confirm if there is a geotechnical report. |
A geotechnical report was not created for this project. Please include this as part of construction testing to be by general contractor. |
Please confirm if there are any unsuitable or contaminated soils. |
Testing only will be the responsibility to be by the general contractor. |
Please confirm there is no asbestos or lead remediation expected. |
Based on previous projects in the building there is no asbestos or lead remediation expected |
Please confirm what door is applicable for section “083113 – ACCESS DOORS AND FRAMES” |
This section is refereing to access doors for mechanical or plumbing items at drywall walls or ceilings to be intstalled as required. |
Please confirm if spec section “099113 – EXTERIOR PAINTING” is applicable to this project, if so, please confirm the scope. |
This would apply to the the structural steel at the exposed steel framing at the roof screen. |
Please confirm if Lake County would be willing to waive the AWI certification – all millwork will be built using AWI standards, however, the county would likely get a more competitive price without the certification. |
Yes, this can be waived. |
Drawing A1.6: The finish schedule on A1.6 lists two CPT-1 but does not list CPT-2. Please confirm. |
CPT-2 should have the reference for the Mohawk, Reckless BT353/883 Wild Thing |
1. Rooms 116 & 117 are tagged to receive CPT-1 on the finish plan but don’t have a demo keynote about removing flooring in the entire classroom. Should the entire classrooms get new carpet and base or only along the perimeter wall that’s being demo’d. (will assume only patching where new wall is being demo’d) |
Reinstall salvaged existing carpet tile as required to patch along the perimeter wall being infilled. |
A site As-Built Survey will be required as part of the contractor's closeout for submittal to the Village of Libertyville. |
A site As-Built Survey will be required as part of the contractor's closeout for submittal to the Village of Libertyville. |
Please clarify CPT-1 & CPT-2 locations on page A1.6 per the legend. They are both called out as CPT-1. |
CPT-2 should have the reference for the Mohawk, Reckless BT353/883 Wild Thing |
Please clarify if we are to use CT-2 in the restroom. It is called out on page A1.6 in the finish Ledgen but no spec is provided. Also, CT-2 is not shown in the elevations on page A4.0. |
Provide CT-1 on floor and walls at Toilet Room 140 |
Please provide floor/wall finish in existing Mechanical Room 135. |
The existing walls are painted concrete block and the floor is a mix of VCT and exposed concrete. |
Revised drawings S1.2 and S2.3 |
See the attached revised structural drawings for revisions to the roof screen. |
Revised formed metal wall roof screen. |
Revise formed metal wall panels per Spec Section 074213.13 at roof top screen to be perforated (23% open area) aluminum 7" horizontal ribbed panel with standard factory finish attached to structural steel framing. Contractor to provide all required trim pieces and access gate. Basis of design www.roofscreen.com 7.2 Rib Panel. |